Laiwu Powder
Metallurgy Company says, "we are satisfied with OTSK service!"
May
24th, 2010, Laiwu Powder Metallurgy limited Company sent to my company
"User Report" (see Annex) which reads as follows:
Tangshan
Outstanding Kiln Limited signed the "No.2 coal burning tunnel kiln gas renovation
contract" with our company on,May. 31,2007. Project started on July 18,
2007.In the morning of August 16, the gas ignited and achieved a one-time
success, after 25 days¡¯ firing and debugging, moved smoothly into production
phase. Practice proves that transformation of the furnace is successful, in
addition to meet the national "industrial furnaces building and inspection
standards" requirements, product quality and production has been greatly
improved after transformation. Without failure caused by design or construction
of the tunnel kiln during warranty period, our company is satisfied with OTSK
service.
Laiwu
Iron and Steel Group Powder Metallurgy Co., Ltd.2010-5-24